What milestone objectives were actually attained?  Be specific!

Milestone for the week is here.


Right now the code for the Search part of this should mostly be complete. However, there are 4 dependences: UI team, Relationship Team, Backend team. At this point, all should be working except the UI team (which I just need to talk to them about how they want to integrate it and send the information.) The sorting is pushed along in the Search tree, attached to parsed variables in the Relationship team and put into SQL there, and passed to the back-end.


Basic functionality that is being included in this version is sort by GlobalRank, Author, Creation Date, and Name (for content) and Name (for Author). We will be adding more and more functionality in future weeks.

What milestone items were left uncompleted?  Be specific!

Testing [coming soon(TM)] and integration with the front end. Otherwise things should be looking good. What exactly does integration with the front end entail--do interfaces need to be designed or simply implemented? A little more detail on integration issues would make this clearer. --Chelsea