M07 11-07-07: View Response #2

Name

Hubert Lee 

Percentage complete

90% 

What milestone objectives were actually attained?  Be specific!

Milestone can be found here.
  • I completed the implementation of the IAccessControlAuthorization interface. This involved introducing a number of permissions-related methods to IBackendObject and retrieving data from the database.
  • Created a permissions table in the database from which to draw permissions
  • I've been working with Dave on the relations team to get support for retrieving the parents and ancestor groups of users and content. This has been a bit difficult, since support for content groups doesn't currently exist. I've drafted a document on our proposed solution here.

What milestone items were left uncompleted?  Be specific!

Many of the methods I implemented have not been tested yet, since my test cases are dependent on the database, which was purged twice recently. Now that the database has data again, I need to rewrite my test cases and then begin integration of permissions into the system. Brad has offered to help me with this.
I'd recommend that you set up some way to automate repopulating the databases after purging so your test cases aren't broken. Also, kudos for having test cases. --Chelsea

Additional Comments

Thanks for fixing your posted milestones.